How to link multiple epics? Does JIRA have a theme/feature concept? I am trying to link multiple epics into one to keep track of the progress! Please help.
Right now it seems you can only move issues in terms of rank one at a time. Is there a way to move more than one at a time? For example we like to keep all of our In Progress stories/tasks at the top...
I am having trouble getting the fields in Jira and Roadmaps to sync as I would expect. I am using estimates in hrs and have my boards set up to do so. In my plans, I have the estimation set to hours ...
Hello, I'm trying out Porfolio/Advanced Roadmaps Server Version 3.1, improved planning interface and don't see the "Progress (story points)" or "Progress (issue count)" fields available to add in my ...
In the Portfolio plan, we get to see the issues with status"Done" and Resolution "Done", But the ones with Status "Done" and Resolution - unresolved (since there is no post function set and there is ...
Hi, I am finding that whenever I check back on an advanced roadmap i've created there are new issues (top of project hierarchy, one level above EPIC) that are added in. The issues have nothing to d...
I am new to Advanced Roadmap and attempting to use the auto-schedule feature. I am having multiple issues with the auto-schedule feature and seeking help. I have a roadmap where I ...
In reviewing some documentation, I get the idea that the program is not just an aggregation of plans, but may calculate differently: Taken from the atlassian page linked below: The end date ...
. It works for 150 days i want to see the done issues for more that a year say 400/500 days. possible ?
Hello, Does auto schedule considering the "Lead" value? I have 2 tasks One should start after the other is finished and the auto schedule not changing the issues start and end date accordingly.. ...
Hi, I'm seeking your guidance. I'm trying to build a plan using the Plan app that will show in the same hierarchy that we have on our Structure board. The logic that we use in our Structure: Ini...
Hello everyone, This question might be basic but I'm new to the Atlassian community. Our team has started using Jira for agile method recently. We work on several projects simultaneously and these...
We're running Jira v8.5.4 and Portfolio/Advanced Roadmaps v.3.26.0 We have several Jira projects (teams), each with one or more project releases for each of the products that team is responsible for...
Hello, I am working within a Plan and seeing that when I Auto-Schedule my plan, Stories currently within an Active Sprint are having the sprint removed. I have the setting set to overwrite all Sprin...
Description is not an option in the Fields LOV. We have a lot of information there, so I'd like to include it in my plan. How can I make it display?
Hello everyone. When I complete an epic, it disappears from the plan view. It is only suppose to do so after 60 days (current setting). The initiative that contains 1 epic which is...
I would like to be able to change the status of a story or sub-task to @'Done' for example. Ideally from within the roadmap itself.
In my Plan view I want to be able to see which teams are assigned to which issues and not have to do this manually. Is there a way this field can be auto-populated based on the following: a) When t...
Hi, I've mapped out my dependencies, run auto-scheduler and everything looks good, except I don't understand why some issues on the Gantt chart have red circles with numbers in. I understand the num...
Hi, We're importing epics and stories with Target Start and Target End dates at the epic level which are correctly represented in the roadmap view. The stories within those epics have time based est...
Hey, can anyone help? we have Jira Subscription, Confluence Subscription, Bitbucket Subscription, and an Advanced Roadmaps Subscription but we don't use Advanced Roadmaps (we think), and its costing ...
Advanced roadmap can't running after install. I try install next versions 3.29.1 and 3.28 and 3.0. And I have the same errors : and Caused by: com.atlassian.rm.common.bridges.jpo1.api.P...
The default working hours per day in our JIRA setup is 6h, in Advanced Roadmaps it is 8h. The problem that we are encountering is that Advanced Roadmaps is taking the estimated hours and converting t...
Hi All, It would be great if someone can throw some insights, on below I am using my Scrum Board fed as input to PLAN in Portfolio. I am unable to see the old Sprints Capacity, whereas I can see on...
I have created advanced roadmaps (which I love BTW) and I like to customize view settings to group by teams to see capacity and color the bars based off of key fields. But, it's frustrating because I...