The default working hours per day in our JIRA setup is 6h, in Advanced Roadmaps it is 8h. The problem that we are encountering is that Advanced Roadmaps is taking the estimated hours and converting them into days which screws up the estimates being shown in AR: An estimation of 5d (30h) in JIRA is being turned into 3.75d in AR. This makes planning difficult.
I am aware that it is possible to display the estimations in hours, but having numbers with three digits for an estimation like 196h, isn't helpful at all for various reasons.
Is there a way to change the default working hours per day in Advanced Roadmaps or inherit the settings from JIRA?
Thank you!
Mark