AsmitaD September 16, 2020

. It works for 150 days i want to see the done issues for more that a year say 400/500 days. possible ?

1 answer

0 votes
Jonny Adams
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 16, 2020

Hi @AsmitaD 

  1. Go to More > Completion date.
  2. Select which filtering time frame you'd like to use for completed issues.

Then,

  1. Go to More > Completion date and open Schedule range.
  2. Select the schedule's range you want to filter by.

Suggest an answer

Log in or Sign up to answer