Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Unable to see Capcaity details of previous sprints in Portfolio

Bhaleeq Ahamed September 3, 2020

Hi All,

It would be great if someone can throw some insights, on below

I am using my Scrum Board fed as input to PLAN in Portfolio. I am unable to see the old Sprints Capacity, whereas I can see only current and Future Capacity data related to Sprints.

 

Thank you

1 comment

Dave
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 3, 2020

The main reason for this is that Advanced Roadmaps is considered to be a forward planning tool. When a plan is loaded it only fetches issues that have been resolved recently (the number of days can be configured for each plan, but defaults to 30). This is done in part to reduce the number issues that are loaded because increasing the number issues loaded will have an impact on the plan loading time (and in fact there are limits on how many issues are supported for each plan). 

The best way of reviewing historical sprint information would be to review the reports available for projects (such as sprint report, burn down report, etc)

Regards,

Dave

Like Bhaleeq Ahamed likes this
Bhaleeq Ahamed September 6, 2020

Thank you so much, @Dave 

Like Dave likes this

Comment

Log in or Sign up to comment
TAGS
AUG Leaders

Atlassian Community Events