For a Company managed project, I want to be able to create a simple hierarchy that does not use an Epic. Reason we have used the Company managed project is because we need to pull issues from ...
We are a huge program with multiple Jira projects involved. We are currently in transition and with a hybrid structure of product teams and initiatives driven directly by product delivery leads (inte...
I cannot figure out if there is a way to set the color of the Initiatives or Epics in a Program roadmap. I know how to do it on the regular Plan roadmap. Also, how can you make the releases show up o...
Hello All, I want to update all child issues of certain epics once. When a story is created or modified, this rule already applies. But I want to do the same once for all alrea...
Hi, I am trying to use the Advanced Roadmap to estimate capacity and plan sprints. When I look at screenshots in help documentation I see additional information in the Sprint Capacity Informat...
We have one project that has a very large number of boards within it. I have created the hierarchy (Theme, Initiative, Epic...) and have been testing using a few of the boards. My dilemma is when I h...
Hello, I'd like to group the issues in the dependency report by a field that is NOT Team. For example, I'd like to group my issues by a label. Is there a way to configure Advanced Roadmaps ...
I would like to add a customers column in a queue in Jira service desk
I need all project tickets via the "Better Excel" format
im group creator, and since last week cant see active sprint and backlog all other team member's can see it no problem i can see road map and can create issues but active sprint page and backlog b...
Currently running on an older version of Roadmaps (8.20.3) I'm trying to get the Resolved date into the plans, but for some reason I am not able to. A workaround would ofc be to set due date as the...
Hi everyone, I work in three different Jira Advanced Roadmaps that are all based on projects that are using the same issue type screen scheme and therefore the same default issuetype. At the moment...
The issues in my filter use the Estimates field in days for the project's estimated time to complete. Is it possible to get the Gantt view to take a start date for an issue and dynamically plot the i...
Background: "Advanced Roadmaps for Jira (ARJ)" is primarily offered as a tool to plan and track work across multiple teams / projects. It can 'pull' and 'show' data from different sources: Projects,...
Let me say up front that we have recently upgraded Jira from data center 8.18 to version 8.22.3, so it is not clear how that affects the issue I am describing. The roadmap Configuration process has c...
Hi, I've noticed that when viewing ongoing sprint form the advanced roadmaps "Allocated hours" reduces every day as the remaining estimate decreases though total capacity does not change. Is this fu...
As per title: It is my understanding, that the "parent link" can only be set on the corresponding child issue (ie. bottom-up). Is there a possibility to link a parent to several child issues or can t...
Dear Team In Jira Advanced Roadmaps, I am able to see "Target Start Date" and "Target End Date" columns by default. I am wondering how to show "Actual Start Date" and "Actual End Date" ...
When auto-scheduling, a number of factors are considered including team capacity. I'm hoping to auto schedule based on task dependencies and estimated durations (days) only. Is this possible? ...
So I made a gadget in my team's dashboard that shows items in order of most recently commented, since we use that for a lot of our notes and updates for issues. This is driven by a custom field calle...
It appears I no longer have the options to create a new "Plan" in Jira. I was just in there yesterday. Is this a permission that got messed with (I couldn't find anything online). T...
My question is a follow up to the following Atlassian Community post: Custom issue and issue hierarchy (atlassian.com) If a custom issue and issue hierarchy is defined using Advanced Roadmaps, is t...
We are using Initiative>Epic>Story>Sub-task in our hierarchy. Is there a way to show the "health" of the Initiative in the roadmap view? We are currently driving everything by Story Points i...
See https://support.atlassian.com/jira-software-cloud/docs/configure-working-days/ Does AR factor this in for capacity planning and scheduling and other planning aspects? I've been trying to g...