Ignore team capacity when auto-scheduling

Lucas Scheer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 21, 2022

When auto-scheduling, a number of factors are considered including team capacity. I'm hoping to auto schedule based on task dependencies and estimated durations (days) only. Is this possible?

 

I'm trying to create a simple schedule without having to manually calculate start and end dates.

1 comment

Comment

Log in or Sign up to comment
Walter Buggenhout
Community Champion
July 21, 2022

Hi @Lucas Scheer and welcome to the Community!

Not as far as I know. Auto-scheduling is a helper tool that - as you rightfully point out - considers a lot of things when creating a schedule. You probably have already found this support article describing a.o. those factors.

There is only a very limited bit of configuration you can do, as described in this support article: determine if you want to override values already present in existing issues or not.

Hope this clarifies! 