I went to an 'in progress' epic to check the total time spent so far. Time tracking: "no time logged", and the "Include subtasks" box is checked.

Currently, two of my three issues in this epic are status:Completed, resolution:Done. Of those two, one of them I entered the time spent when I was marking the resolution. So I didn't use the "log time" function, just filled in the time spent when I was closing it out. 

What might be preventing the epic from showing the time spent on subordinate issues? The time I entered was 20m, is there a hidden rule that an epic needs to round to the nearest hour? 

2 answers

0 votes
RVS_Support
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 18, 2023

Hi @Dan Tork 

If you would be interested in a ready made solution, you may want to try out our add-on to manage multiple Epics and their hierarchy on a single page.

Epic Hierarchy is made available on Epic Issue screen as well by the add-on

Agile Tools - Epic Tree and Time in Status 

Manage and visualize your Epics with rolled up estimate progress reports.

Disclaimer : I am part of the team which developed this app

Epic Hierarchy - Gadget - Summary.PNG

0 votes
Dan -minware-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 16, 2023

Disclaimer: marketplace partner!

Hey @Dan Tork - this has been an ongoing issue; here is a resource for you to check out:

https://community.atlassian.com/t5/Jira-questions/Epic-amp-Story-time-tracking-roll-up/qaq-p/1340019

If you are looking for a solution, we can help at minware - we have a proprietary time-allocation heuristic that allows us to automatically calculate this for you based on commit activity; you can see the "roll-up" of time in the screenshot below:

Let me know if you want to check it out!

Dan

 

atlassian_commits.png

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events