I want to set start date automatically when ticket moved to in progress

Burak Serkan Sertbarut November 27, 2022

Hi,

I ve seen similar topics in community however I couldn't fix the issue event I read and apply these suggetions.

Reference: issue 1 and issue 2

So, I ve created a rule but it doesn't work. I ve checked the rule detail and also checked atlassion-addons-project-access as mentioned in issue 1 and issue 2.

How can I solve it?

Thank you in advence.

 

image.pngimage.pngimage.pngimage.png

1 answer

0 votes
Charlie Gavey
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 27, 2022

Hi Burak,

Are you able to share a screenshot of what you're seeing in the Audit Log for this rule, to confirm whether the trigger is working as expected? 

https://support.atlassian.com/cloud-automation/docs/what-is-the-automation-audit-log/

Cheers,

Charlie

Burak Serkan Sertbarut November 28, 2022

Hi Charlie,

Thank you for your answer. Here is audit log shows "success" status for rule.

image.png

Burak Serkan Sertbarut December 5, 2022

Hi @Charlie Gavey ,

I have shared screen shot for audit logs which seems as in "success" status. Do you have any idea what this issue is about?
Thank you so much.
 

Charlie Gavey
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 6, 2022

Hi @Burak Serkan Sertbarut - can you clarify what you mean by the rule not working? Is the value of "Actual start" not being updated at all, or being updated to an incorrect value? 

Burak Serkan Sertbarut December 7, 2022

Hi @Charlie Gavey ,

Thank you for your answer and caring about this issue.

"Actual start" value is not updated when rule triggered.