can someone explain why the following smart values don't work/ don't return a result?
I need the following calculation "End Date" = "Start Date + 4 weeks". My problem is, that the start date which the Team sets isn't always the same day - That's why I want to avoid replacing "issue.startDate" with "now" as smart value
According to the Log, the rule was successfull, but when I check the "End Date" field in the ticket, the field is empty.
However if I replace "now" with "issue.startDate" the automation rule actually works and returns the correct date. Using only "start.Date" doesn't work either.
Thanks for your feedback!
thanks for your response. That was actually the only option, which I haven't tested out and it worked!