Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,360,972
Community Members
 
Community Events
168
Community Groups

Automation sub-task linking and auto populate start date / end date

Edited
fustyler I'm New Here Aug 25, 2022

Hi, I have automation currently working which creates a list of sub-tasks with issue created as a project. The issue itself sets the start date and end date of the project.

Assuming sub-tasks are completed in a serial manner (eg sub-task 2 starts after sub-task 1 completed), is there anyway to auto-populate all sub-task dates and set duration for each sub-task when an issue/project is created?

sub-task 1 reads the start date of the project from issue start date , end date would be start date + 5 days (standard duration)

sub-tasks 2 start date is end date of sub-task 1, end date would be start date + 5 days (standard duration)

Thanks in advance.

(Jira service desk being used on Jira server).

0 answers

Suggest an answer

Log in or Sign up to answer