Hello - Any thoughts on adding predecessor/successor functionality within Advanced Roadmaps? Predecessor/successor functionality should shift dates as stories are scheduled into sprints. I envision using this functionality at higher levels in the plan.
I found this work around however being able to add predecessors/successors is key to doing long term planning. I'd be fine with using blocks and blocked by if the dates moved. I'm managing a project with 10 different technical teams and need to understand when one teams dates shift how it impacts the entire project.
Successors / Predecessors in Advanced Roadmap (atlassian.com)