Hello,
I have a task "A" that starts on March 1, 2022, and ends on March 5th, 2022. This task is a predecessor of task "B" which starts on March 10, 2022. The lag time is 5 days between the tasks.
Now the puzzle starts... When I change the start date of Task "A" from March 1 to March 8th the start date for task "B" remains the same BUT it should be automatically be updated to March 13th.
Please, explain to me what I am doing wrong
Thank you in advance
It can be achieve via automation.
Step 1: Create Custom Field (Label Type) name as predecessor and add the issue key of predecessor issue.
Step 2: Create automation rule when Predecessor field edit and is not empty then Lookup issue for and use the smart value of Predecessor field.
Step 3. If lookupissue size equals 1 then edit the current issue Actual start date with a smart value "{{lookupIssues.Actual End Date.plusBusinessDays(1)}}" and set the end date as {{lookupIssues.Actual End Date.plusBusinessDays(issue.customfield_10212)}}.
Am I considering that the connection between Task A and Task B is block by/ is blocked by?
If yes, i think there's no way for the automation.