I have three impediments created under my program, one story impediment and two team impediments. The teams related to the impediments (including the story) are all represented in the program room vi...
Hi there, We have about 10 release trains delivering on a 2-weeks cadence. Our release notes are sitting in custom fields in Jira. Would I be able to create 1 or more customized release notes commun...
In the article Plan Capacity for Team and Programs it states "Important: The Use Current FTE button overrides the Planned FTEs boxes with the values from the Curren...
Hi! We have in company ~1100 employees. Our instances are 2k tiers. After looking into pricing model: https://www.atlassian.com/software/jira/align/pricing Looks like...
How to remove a member from an Agile/Kanban team under the <members> tab. As a Scrum master, I want to keep my team clean. If a team member has moved from one team/program to another, how do I ...
To have a better understanding of orphaned work and prevent it from costing you Millions of dollars of delivery capacity, visualize the problem/opportunity. You might find orphans before is too...
Do we have Program Increment Progress reports representing trends of last 3 or 6 PI's around velocity, features delivered etc. Also is there a Cumulative Flow Diagram report for Program Kanban
We have integrated Jira Align and Jira Cloud. Using Atlassian best practices - wherein we have a separate Jira project for features (Jira Epics) and multiple Jira projects for Stories, Defects etc. ...
There are several key distinctions between Objectives and Themes in Align, and people ask “Should I use an objective or a theme?” As we say in our house, why not both? In Align, Objectives and Them...
Can you explain what Jira Align offers that is not available in Jira Advanced Roadmaps?
Can you please elaborate on how to create PI checklist to show up in program room?
My ART includes 10 teams, of which 5 teams use JIRA scrum boards and 5 use JIRA kanban boards. Regardless of scrum or kanban, all of the teams point their stories. Some of our kanban teams make...
I am working on score cards in JA, so just i want to know the functionality of score card, how it works.. Just want to know that which roles are score card is used in JA. any related document is much...
Hi Team, I am working on score cards in Jira align, so just i want to know the functionality of score card & how it used & which roles are we using in JA.. Regar...
I am working on Checklists and have created some checklists that I would like to delete. Can you help me with that please? Thank you.
I am trying to figure out how to show dependencies from JA to Jira for Features. Thanks.
I have created a few external reports via Iframe. Here are a few questions. how do I delete or update External Report tiles? If I turn off External Reporting in Iframe, it deletes all URLS but it ...
We have a usecase where we have to fetch JIRA-Align discussion data for compliance reasons. there is no API call that fetches that information today. But that information is present in LEO Data ware ...
Hi all, I would like an advice from Jira Align experts out there on how to effectively track release (fix version) progress / statuses across multiple programs. I am overseeing multiple pro...
Purpose: Integrating Jira with Jira Align is a multi-phase process. Establishing the connectivity, checking the health of the projects and boards to be integrated, and configuring the connect...
Hi, I am migrating our 2020 stories from Rally and would like to create previous sprints to for these stories, mark them as complete and view them in the sprint report along with my new Jira A...
Hi all! :-) I am looking for the state changes of Jira Align Features & Epics. However, I haven't found it in the REST API yet. Little bit more context: We would like to measure the time...
Best Practice #1: The transition for the "Done" status of stories must have a Post Function of, "The Resolution of the issue will be set to Done." This also applies to all custom issue types ...
We are very excited to roll out some big changes to the Estimation Conversions settings menu. Many of you have voiced concerns that one estimation conversion for all types of work items is an inhibit...
We have two instances: one is General and one is InfoSec. We DO want managers to be able to see metrics for both instances in Jira Align. We DO NOT want (some) managers to see issue level detail for ...
User | Count |
---|---|
2 | |
2 | |
2 | |
1 | |
1 |