The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

How to generate sprints in jira align for sprints with different cadence?

sachin gangam
Contributor
November 5, 2021

Hello All,

Happy Friday!

I have below sprint cadence for a PI and I want to know what is the best way to generate sprints in Jira align. As sprint duration for 2021.PI6.S4 is 5week days.

I was thinking to mass add for S1-S3 with PI start date: Nov24, 2021 End Date: Jan4, 2022 and then single add for S4. ? But, my question is can I change PI end date to Jan11, 2022 after I generate sprints for S4?

 

2021.PI6.PORTFOLIO

2021.PI6.S1 ( Nov 24-Dec 7)
2021.PI6.S2 (Dec 8-Dec 21)
2021.PI6.S3 (Dec 22- Jan 4)
2021.PI6.S4 (Jan 5-Jan 11)


Thanks,
Sachin.

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Tina Behers
Community Champion
November 5, 2021

Absolutely! You can and should!

1 vote
Answer accepted
Samit Mehta _321 Gang_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 5, 2021

Hello Sachin,

You can and should absolutely update the PI start / end date to match the dates you set up the Anchor Sprints / Iterations.

Sincerely,

Samit Mehta, 321 Gang