The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

If an ART requires different start and end dates for a PI, would it require to create new portfolio?

Vinay Sharma
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 16, 2021

If an ART requires different start and end dates for a PI (in comparison to other ARTs in the portfolio), would it require to create new portfolio to accommodate it: pls. suggest

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Rich Sparks
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 17, 2021

ARTs can have different start and end dates within the same portfolio. There's no need to create a new portfolio to accommodate that one ART.

The only thing you'll need to make sure people are aware of is when they want to look at views for the entire Portfolio (for example, looking at the Roadmap view), they'll need to include the PIs for all the different ARTs within the Portfolio. So if your Portfolio has two separate PI schedules, you'll want to make sure you include the two different PIs in the Tier 1 filter.

Vinay Sharma
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 17, 2021

Thanks! @Rich Sparks 