The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

What would cause a dip in EV (Earned Value) (Tempo Budgets)?

Ruth Powers
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 23, 2020

I am trying to find the issues that caused the pictured dip to occur and to prove my theories on why it happened. Does anyone have any suggestions? Additionally , here are my theories am I totally incorrect? 
Theory one: Issues moved from a closed state back to an active state, however, those issues are not back to a closed state and the earned is not lined back up. 
Theory two: Story point values were changed after the issue was closed.
2020-09-23_7-42-41.png

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Alexander Eck [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 23, 2020

HI Ruth,

it depends of course on your configuration settings. But given the scenario that you have chosen story points as your effort field and you set a non-progressive effort both scenarios could be true. In the non-progressive evaluation you will earn value when an issue gets resolved. Means at the end we could add another third theory: some issue statuses of your scope are no longer considered as resolved.

Hope that helps rather than confuses you.

BR

Ruth Powers
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 23, 2020

So, if I when I started say a state is closed, but then edit configuration later it would cause this dip?

Alexander Eck [Tempo]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 23, 2020

No. Not in this case