The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to migrate data from one project to another?

Aaron Monilal
August 24, 2021

Hi all,

We have a team managed (Kanban board) project that we want to migrate the data in to a company managed version - so we can get some more functionality out of it compared to the lite team version.

How do we transfer over the epics/stories/bugs/fields/etc to the new project without having to manually add things back in?

Many thanks!

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Jack Brickey
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 24, 2021

You might find this article helpful - migrate-between-team-managed-and-company-managed-projects 

it is certainly a manual process and not perfect as some things can’t be easily transferred in the”move” process like custom fields.