The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to cross information between story point and jira tempo ?

Patrick Valibus
March 16, 2021

Hi,

I had like to track on a regular basis, the time tracked for a task in tempo and compare it with the story point of this same task.

How can i do that easily ?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Ignacio Pulgar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 17, 2021

Hi @Patrick Valibus ,

The easiest way I can think of would consist of:

1. Run the following JQL query by using the advanced mode of the Issue Navigator:

"Story Points" > 0 AND Timespent > 0

2.  Save your query as a filter.

3. Set the columns to be shown in your filter with at least: Issue Key, Summary, Story Points, Timespent.

4. Export the returned issues to your favorite spreadsheet software and create a column with a formula that calculates timespent column divided by story points column. After that, use a function to show the average timespent per story point.

Hope it helps.