The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to create Epic Link field in Story for Next Gen projects ?

prashantgera
May 24, 2021

I have just created a Next-gen project nd have created few stories in it and an Epic too but I don't find any option where I can link stories to the Epic. Help please.

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Answer accepted
Walter Buggenhout
Community Champion
May 24, 2021

Hi @prashantgera,

The most practical way to add stories to Epics is to start from the Epic and then add them as child issues.

However, when you created a story without an Epic linked to it, open that story in detail view. Then, from the title bar you can select Add Epic:

Screenshot 2021-05-24 at 14.29.16.pngIn the screenshot above, you'll notice the option at the top, to the left of the issue key.

Hope this helps! 

prashantgera
May 24, 2021

Thank you so much for the detailed answer. It helps