Scenario: After bulk move, example issue GEN-123 becomes ULE-123. Then we delete GEN project.
Question: If we search for GEN-123, will ULE-123 show up, since GEN is already deleted? Does the link between the two project keys remain even though GEN no longer exists?
hi @vishal03kadam,
I found a similar community question. there @Nic Brough -Adaptavist- says as below,
The move is simple - both ends of the link stay with it. Anything linked to OLD-10 will show NEW-20 on it as a link (it's not redirected though, the links are held as issue-id to issue-id so the view hasn't actually changed! Redirection only happens if someone goes to the old URL for OLD-10).
Deleting the OLD project will have no effect, you lose nothing.
Unless you create another new project called OLD, then when you hit OLD-10, your redirection will stop working. But your link between NEW-20 and other stuff will be fine.
Reference: What happens to the old JIRA link after you move an issue to another project?
hope you found this helpful! 😊
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Glad to hear @vishal03kadam 😊
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.