Hello
I seem to recall that I was able to easily move Tasks between Epics, but this does not seem to be the case any longer.
Scenario:
I use an Epic as a container for tasks. For example July 2024 Development. As July has gone, and I am starting August, I created a new Epic to move the remaining tasks (not Done) to the new Epic - August 2024 Development.
When I look at task as Children in the Epic, this cannot be changed.
When I view them in Search mode, the Parent appears, but cannot be modified.
The only way is to enter individual Tasks and change them in the Parent field.
I did not manage to get Bulk change work, perhaps this is the way.
Any thoughts?
Community moderators have prevented the ability to post new answers.
Quickest I've found is to use the timeline view to just drag n drop Tasks or Story from Epic to Epic.
Also I get a pen icon when hovering over the Epic breadcrumb which allows me to change the Epic
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Worked for me! Thank you, Lisa 💪
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The quickest way I found was the burger icon top right of the "issue" view, then look for "Change parent" option.
(We don't use timelines Lisa referred to.)