The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

EXT on sprint in Jira Plans?]

Chuck Oleary
Contributor
April 21, 2025

I cannot seem to find anything on why my sprints in Jira Plans show the EXT on them.

My plan uses a scrum board based off a filter as the data source.  It's the same setup as my current plan that does not show the EXT on the plan.

Plan_EXT.png

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

4 votes
Answer accepted
Trudy P Claspill
Community Champion
April 21, 2025

Hello @Chuck Oleary 

Refer to this document for information on the EXT lozenge next to Sprints in a Plan.

https://support.atlassian.com/jira-software-cloud/docs/what-are-external-sprints-in-advanced-roadmaps/

Chuck Oleary
Contributor
April 21, 2025

Thank you!  

I looked for some documentation and this is what I needed!

Like Trudy P Claspill likes this
Trudy P Claspill
Community Champion
April 21, 2025

You're welcome!