Hello,
I am trying to improve our Sprint Board overview.
As we are working with timeline and sprints and only the epics have due dates in our system, I would like to use a query to represent card colors for stories based on parent(epic) due dates and on open dependencies within the stories.
For example: duedate of the epic of the respective story is in 3days and the story has 3 tickets left in the linktype dependency "blocks" then we would like to show the card in red.
Thanks in advance.
Community moderators have prevented the ability to post new answers.
Hi @Sara Pfannkuchen -- Welcome to the Atlassian Community!
A query like that is not possible with out-of-the-box features of JQL, and so it could not be detected for card colors with JQL.
As workarounds, you could...
Kind regards,
Bill