The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

Automation: When Epic is created -- transition parent to intake completed

Breanna Williams
Contributor
May 11, 2023

***I am in a company managed project***

  • When an Epic is created at a later time (parent link field is selected on screen during creation)
  • I would like for the Parent (Legend custom issue type) to transition to 'Intake Completed'

I have tried a ton of combinations and nothing will execute. Audit log continues to say 'No actions performed'Screen Shot 2023-05-11 at 12.01.04 PM.png

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Trudy P Claspill
Community Champion
May 11, 2023

Hello @Breanna Williams 

Can you share with us the details of the Audit Log?

The status of "No actions performed" indicates the rule was triggered but that some condition in it was not met. The Audit Log will show those details.

I suspect the problem is that you selected Parent for the For Related Issues branch. Notice that Parent applies only to finding the parent of a subtask.

Screen Shot 2023-05-11 at 10.19.55 AM.png

 

You instead need to do this:

Screen Shot 2023-05-11 at 10.23.39 AM.png

Breanna Williams
Contributor
May 11, 2023

Oh it worked!! Thank you for you help (yet again) @Trudy P Claspill 

Like • Trudy P Claspill likes this