***I am in a company managed project***
I have tried a ton of combinations and nothing will execute. Audit log continues to say 'No actions performed'
Hello @Breanna Williams
Can you share with us the details of the Audit Log?
The status of "No actions performed" indicates the rule was triggered but that some condition in it was not met. The Audit Log will show those details.
I suspect the problem is that you selected Parent for the For Related Issues branch. Notice that Parent applies only to finding the parent of a subtask.
You instead need to do this:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.