Hello Jira experts,
Is there any way to move issues within the Kanban board based on date filters. For example move issues from To Do to Done after it's been open for 30 days, yes i know fundamentally this doesn't make sense but i;m just wondering.
"To Do" : Any items older than 14 days (created date) is move to the Done column
In Progress: Any items older than 30 days (created date) is move to the Done column
Or perhaps there's a way to modify the workflow with conditions or triggers.
Thanks for all your help.
HI Richoo,
To transition an issue based on a time event you are going to need an add-on app that that can automate the the transition.
Check out the following post on this noting three add-ons that have this capability and examples on how to set it up with each:
Regards,
Earl
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.