Hello,
In my avanced roadmap (Plan) hierarchy I have at the high level the Initiative issue type and below the Epic. Initiative is in the project WALLET Epics are in many projects.
I am struggling to create 2 automations
First
If all the Epic of a given Initiative are in one of these status in ('PO Review', 'IT Review', To Plan') I want my initiative to transition from Open to Qualification.
Second
If one Epic of a given Initiative is in the status = "In progress" then Transition the Initiative to "In Developement"
So far I have tried to create an automation checking the transition of the Epic into one the status then I create a branch with a JQL but I'm kinda lost...
Someone can help?
Hi @Philippe Puy -- Welcome to the Atlassian Community!
For a question like this, context is important for the community to help. Please post the following:
Until we see those...
There are several built-in template rules you could use as a starting point. You may find them under Templates in the rule list. One such example is named:
When all child work items are completed → then close parent
Kind regards,
Bill