I am interested in whether in the road map dependent tasks can be automatically transferred if the previous task is delayed?
Hi @Оля Соловей -- Welcome to the Atlassian Community!
You appear to be using the free license of Jira Cloud, and so are using the Basic Roadmap feature. On this version, epics are displayed based upon the Start Date and Due Date.
There is nothing built into the roadmap to handle shifting those dates based upon late issues, however you could build an automation for Jira rule which runs on a schedule and adjusts the dates accordingly.
If this is something you want to learn about and try, please review this documentation and examples: