how to estimate the sprint correctly

I am product/project manager and need to create sprint for development team. How can I create more accurate sprint?

1 answer

0 vote

Hi Cindy,

That's a very open question. There's a lot of questions one can ask in return. However, I guess the baseline would be to measure and adjust accordingly.

A good starting point might be the Velocity Chart (See documentation over here). It will compare your commitment to your actual performance. And it will keep track of that performance over time.

From the data you gather from past performance, you will be able to predict better. And also improve the estimation skills and ceremonies within your team.

Thanks Walter. I am trying to learn Jira more.

 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published yesterday in Off-topic

Get to know our Atlassian User Group Leaders from Bengaluru, India

Meet @Dinesh Dhinakaran, @Vishnu Vasudeva, @Rajeev Verma, and Jamshid Nalakath: Our extraordinary AUG leaders from Bengaluru, India. These four work together to strengthen the bonds of their local co...

146 views 0 4
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you