how to estimate the sprint correctly

I am product/project manager and need to create sprint for development team. How can I create more accurate sprint?

1 answer

0 votes

Hi Cindy,

That's a very open question. There's a lot of questions one can ask in return. However, I guess the baseline would be to measure and adjust accordingly.

A good starting point might be the Velocity Chart (See documentation over here). It will compare your commitment to your actual performance. And it will keep track of that performance over time.

From the data you gather from past performance, you will be able to predict better. And also improve the estimation skills and ceremonies within your team.

Thanks Walter. I am trying to learn Jira more.

 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Featured Groups

Tuesday tips & tricks: What is the Atlassian Community?

It's officially Tuesday, which means it's officially time for another tip to help you better navigate this space we call the Atlassian Community. 😄 I got a great question from community member, Sa...

116 views 6 8
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you