how to estimate the sprint correctly

Cindy Feng April 25, 2017

I am product/project manager and need to create sprint for development team. How can I create more accurate sprint?

1 answer

0 votes
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 25, 2017

Hi Cindy,

That's a very open question. There's a lot of questions one can ask in return. However, I guess the baseline would be to measure and adjust accordingly.

A good starting point might be the Velocity Chart (See documentation over here). It will compare your commitment to your actual performance. And it will keep track of that performance over time.

From the data you gather from past performance, you will be able to predict better. And also improve the estimation skills and ceremonies within your team.

Cindy Feng April 25, 2017

Thanks Walter. I am trying to learn Jira more.

 