How to instert start and end date into and issue?

Hi, I was wondering if it was possible to create a start and end date on an Issue? When we sync the Jira projects to BigGantt, all the issues are placed onto the first date rather than the date we would like the Issue to be worked on.

Thanks

1 answer

I don't see that you've gotten an answer yet, so:

you have a choice:

A. modify the start/end dates AFTER you create the BigGantt.  In BigGantt you can click and drag the bar on the Gantt to reposition its timeframe.

B. modify the start/end dates in JIRA.  To do so you must first define the start and end date fields in your BigGantt configuration. Do this through Addons-->BigGantt-->Gantt configuration.

then, add the Start Date and End Date fields into your screen and screen scheme.  

more info here

https://softwareplant.atlassian.net/wiki/spaces/BP/pages/74416222/Global+whole+plugin

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted 12 hours ago in United States

Administrators Cleanup

Good morning, After a long weekend cleaning up, I am still in the cleanup mode 😊. I am curious to know: When do you feel the urgency to cleanup your Atlassian Tools? How many times do y...

16 views 0 0
View post

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you