The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How do I create a sprint in the past.

Todd Rinaldo
August 27, 2012

I've imported my user stories from another system, but I cannot seem to add them to a sprint dated in the past. I get the error: "You must specify a start date that is not in the past.". How can I work around this to import past sprints?

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
James Sandlin
August 27, 2012

Create a sprint NOT in the past. Drag your tasks into said sprint. Update said sprint to be a past date. Close said sprint.

Todd Rinaldo
August 27, 2012

Yep. I'm trying to import 10 sprints from another system.... PAINFUL!!!!

Jeff Isenberg
Contributor
October 23, 2012

This doesnt work for me as the end date always gets updated to the current date when I close the sprint, even though I set it to a past date.

0 votes
Jeff Isenberg
Contributor
October 1, 2012

Is there any way to use bulk update?