How can I make to create task by default in custom Status?

Everytime I create a task, gets the status "to-do" but I need it in a custom one (ice box) is that possible to configure?

Thanks.

1 answer

1 accepted

1 vote
Accepted answer

Assuming you mean JIRA, then yes.

Have a look at the "workflow scheme" for the project, which will tell you what workflows are in use.

Find the one for "task" and make a copy of it in the admin screens.  Add the new ice-box status to it and change the "create" transition so it lands there instead of to-do

Go back to the workflow scheme and add the new workflow, and associate it with tasks.

Yes, sorry, JIRA!

 

Thanks for your quick answer, it works!

Best Regards!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Friday in Jira Service Desk

Looking for anyone who has switched from Zendesk to Jira Service Desk

Hi Community! The Jira Service Desk marketing team is looking for customers who have successfully switched from Zendesk to Jira Service Desk!   We’d love to hear your thoughts on the pros and ...

44 views 2 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you