Hi,
I think I using greenhoper workflow ( I have 3 columns- To do, In progress and Done).
I define time estimation only to sub tasks.
I using structure plug-in to connect between Epics, stories and tasks.
The problem is that I can't dragging a parent issue from "To do" to "In Progress" before i finished all his sub tasks.
I want the possibility to move Epic, Story and tasks that connected together when I started to work on the first task.
please advise,
Nirit
Hi Nirit,
I know that it is been a while this topic open, I would like to give my opinion for your issue.
It appears that this is an expected behaviour for Greenhopper, as when a issue is having a sub task, the parent's status will be dependent to the sub-task. Also, it will transition only when all the sub-task is already resolved or done.
You may would like to check this Knowledge Based article that we have:
Hope this at least could help you.
Best Regards, Julian.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.