Can a sprint's original scope be manually edited?

Jason Tolliver April 28, 2017

I understand that the biggest worry in a sprint is scope-creep so you wouldn't normally want to do this.  However, I've occasionally started a sprint and then realized that there were a few stories we forgot to estimate story points for.  Now I can't add that without completely screwing up the burn-down chart.

I understand you're trying to encourage best practice here, but now I can't actually follow those practices because of the restrictions in place.

Am I missing something?

1 answer

0 votes
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 29, 2017

Hi Jason,

The burn-down chart is just a report. It just reflects what you do. So indeed, if you change estimates on issues already in your sprint, this is reflected in the chart as an increase in story points. Simply because that's what it is.

I would not call this restrictive. There is nothing that blocks you to add or change estimates already in the sprint. There is also nothing that stops you to remove issues from an active sprint either.

The fix here would be to avoid that you start a sprint without unestimated items in them. So include a check of all planned items in your planning ceremonies before you actually start the sprint.