Can I edit date in a completed sprint?

pitchumani
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 30, 2012

I'm using JIRA v5.1.4

1 answer

1 accepted

3 votes
Answer accepted
OmarA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 30, 2012

Hi,

Actually in GH is not possible to change the date of the completed sprints since the completed sprint will considered as "released".

Cheers,

Omar