Can Due Date of an Epic be updated based on the Due Dates of its child items?

Hi guys - I am looking to have 'Due Date' field of an Epic updated automatically based on the information I have for its child items.

For example: If Due Date of Task 1, linked to Epic A, is January 29th, I want the Due Date of the epic to be January 29th. If I create another task under this epic, Task 2, with a date of March 3rd, I want Epic A to show its Due Date as March 3rd.

1 answer

0 votes
Kevin Bui Atlassian Team Jan 14, 2020

Hi @Federico Rocca - I don't think this functionality is available in Jira out-of-the-box. I believe there are Marketplace apps that allow you to do this, but I don't have any experience with those.

Thanks Kevin. 

Suggest an answer

Log in or Sign up to answer
Community showcase
Published in Next-gen

Next-gen Customer Council

Hey Next-gen fans, Would you like the opportunity to give direct feedback to the Next-gen product team? Would you like the chance to preview and test new Next-gen features? I’m excited to annou...

1,042 views 13 26
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you