From within the view issue screen (i.e. https://liveops.atlassian.net/browse/xxx-yyy) can you make the sub tasks show the remaining estimates in numbers without hovering over the graphical bar?
Hi Yen. You can edit the jira.table.cols.subtasks
in your JIRA Admin > System | General Setings > Advanced Settings to show Remaining Estimate as well or instead of Progress. If you have not done this before though, I strongly suggest that you change it in your sandbox instance before playing around with it in your actual instance
It should be remainingEstimate
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The value "timeestimate" worked for me.
For orginal estimate use "timeoriginalestimate".