is there any relation between the work estimation on the issue and the subissue?

This question is in reference to Atlassian Documentation: Creating issues and sub-tasks

I use subissues to split work in relation to different work packages.

For example
subtask1 for coding

subtask 2 for testing

subtask 3 for writing the documentation

on the main issue I would like to see the time changes influenced by the subtasks.

Is there any way to do this?

1 answer

1 accepted

0 vote

No, there is not really.

Plain JIRA (not Software) does have a roll-up mechanism for estimates and work logs, such that a parent issue can display the sum of all the estimates and work logs for itself and its children, but altering the estimates on a child has no effect on the parent, other than that display (which you can toggle between "parent only" and "parent and all subtasks")

But that's it.  The estimates for each issue are for that issue and don't affect other issues in any way.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Apr 17, 2018 in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

795 views 2 19
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you