Workflow status with a category of DONE does not appear as DONE on burndown chart/reports... why?

Tina Pitsiavas February 22, 2018

Prior to this upgrade of Jira interface.. any workflow status with a category of DONE showed in the burn down chart. Now.. only ARCHIVED workflow status which has the same DONE category appears as burn down.

What's happened??  These reports are useless to us now as we don't get a visual indication of whats been happening in the sprint.  Is anyone else having these issues with this new interface?? how do we fix this?

 

1 answer

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 22, 2018

Is "DONE" the right most column on the board? A board considers the story as done or finished when it reaches the right most column and that is when the burn down happens.

Tina Pitsiavas February 25, 2018

Thanks Jobin... that fixed that problem.. however, am pretty sure, previous to this new interface.. that didn't seem to be the case. Anyway, all good now.

Tina Pitsiavas February 25, 2018

btw.. the DONE column wasn't the problem. It was the status with a category of Done which was in the second from last column because of how we set up our workflow.

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 25, 2018

It's been "done = right hand column" since Jira Agile created the Scrum boards and dropped rapid boards, so I assume your fix is to get the status into the right column.

Tina Pitsiavas February 26, 2018

Yes.. correct Nic.