Why don't our versions/epics show any progress?

Micah Mutrux June 9, 2015

I've modified our workflow to better suit our deployment routine, but in the process I think a few things were left behind.  Right now the only Version or Epic that is showing it's progress on the backlog view is our first Version ("MVP").  You can see that it considers several stories complete:

image2015-6-9 17:22:15.png

I'm not sure what the difference is - the story status' all look correct to me.  And if I click through to the Version details page, it seems to recognize completed stories as such:

image2015-6-9 17:24:40.png

What is it that JIRA uses to signal progress for Versions & Epics on the backlog page?

1 answer

1 accepted

2 votes
Answer accepted
Christian Czaia _Decadis AG_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 9, 2015

What I can see that the "Estimate" field is empty. Do you have your estimation statistic set to story points for example and haven't actually added story points? In that case you won't see the completion bar...

Maybe turn your estimation statistic to issue count and see if that works?!

Cheers

Micah Mutrux June 25, 2015

Yep - you're dead on. Thanks.