Why don't our versions/epics show any progress?

I've modified our workflow to better suit our deployment routine, but in the process I think a few things were left behind.  Right now the only Version or Epic that is showing it's progress on the backlog view is our first Version ("MVP").  You can see that it considers several stories complete:

image2015-6-9 17:22:15.png

I'm not sure what the difference is - the story status' all look correct to me.  And if I click through to the Version details page, it seems to recognize completed stories as such:

image2015-6-9 17:24:40.png

What is it that JIRA uses to signal progress for Versions & Epics on the backlog page?

1 answer

1 accepted

What I can see that the "Estimate" field is empty. Do you have your estimation statistic set to story points for example and haven't actually added story points? In that case you won't see the completion bar...

Maybe turn your estimation statistic to issue count and see if that works?!

Cheers

Yep - you're dead on. Thanks.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Sunday in Agility

You asked for it, so we delivered: images on issues have arrived

A picture tells a thousand words. And agility boards have just released their latest feature: cover images on issues – so now your board can tell a story at first glance. Upload attachmen...

164 views 1 10
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you