The problem is as below
1. The story is created and assigned to a developer [Status: New]
2. User Story point are allocated as per estimation [Status: New]
3. Developer starts working on the story [Status: In Progress]
4. Developer moves to [Status: Code Review]
5. Developer changes the Assignee to QA [ Status: Ready for QA]
6. QA works on it and closes it [Status: Done]
problem statement: how do I track the effort of QA and DEV separately if that is possible in terms of Story Points when one story/task is moved between DEV and QA as all tasks finally end up in QA bucket
Hello @Karthik Giridharan ! Welcome to the Atlassian Community!
Story points should be an estimate of TEAM effort to complete a story, including development, QA, and deployment.
I wouldn't try to try to divide up story points between different efforts.