What is the reason for the update the Original estimate

Valeriy Kosenko March 25, 2023

Hi, everyone,

I noticed the following situation in one of Story at night or early in the morning the Original estimate was increased on my behalf.

 

Screenshot 2023-03-25 at 16.28.23.png

I changed the Original estimate, but it increased again

Screenshot 2023-03-25 at 16.30.20.pngScreenshot 2023-03-25 at 16.29.05.png

I checked the values of the estimates of the child issues, but they do not have such large values.

 

This is the first and only case among many issues, and this has never happened before.

I would be very grateful for your help or a hint on where to look for the cause.

2 answers

2 accepted

1 vote
Answer accepted
Benjamin
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 25, 2023

Hi,

 

I may have to do with an add-on. Do you have any add-ons in place?

 

See this post if you have a similar issue:

 

https://community.atlassian.com/t5/Jira-questions/Original-estimate-keeps-changing-back-to-old-value-when-trying/qaq-p/1400059

 

-Ben

Valeriy Kosenko March 27, 2023

Hi, @Benjamin 

Thank you for directing the search for the cause. I think I found the cause and how to fix it - see the screenshot below.

EndDate=OE_Sum_without_parents.png

I'll see what happens tonight and let you know the results.

Valeriy

Like Benjamin likes this
Benjamin
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 27, 2023

Awesome. Glad you narrow down the possible cause!

Valeriy Kosenko March 30, 2023

Hi, @Benjamin 

All these days, I tried to fix the problem but could not.

I can manage the Original Estimate in Big Picture.

Screenshot 2023-03-30 at 14.13.10.png

 

Screenshot 2023-03-30 at 14.15.12.png

 

But after changes, the Original Estimate in Big Picture does not automatically change the Original Estimate in Jira.

Screenshot 2023-03-30 at 14.17.36.png

 

I manually changed the original estimate in Jira, but Big Picture automatically returned it to its original value.

Screenshot 2023-03-30 at 14.20.34.png

Big Picture settings are as follows

Screenshot 2023-03-30 at 14.21.59.png

 

I'm glad to hear any thoughts on where to look for the cause.

Valeriy

0 votes
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 25, 2023

Who does the issue history name as the person who changed the estimate?

Valeriy Kosenko March 27, 2023

@Nic Brough -Adaptavist- 

Thank you very much for responding and asking your question.
The answer to your question is in the screenshot below.
Who does the issue history name.png

 

Please read my answer to @Benjamin; I think I found the cause and how to fix it.

 

Valeriy