I have a user who is receiving "We couldn't create the subtask. Check your connection, then give it another try", when attempting to add a subtask to a software project board.

 

I saw the workaround for this issue which is:

  1. Click on Actions from New Issue View.
  2. Select See the old view.
  3. Again click on Actions.
  4. Select Create a sub-task.
  5. The form pops up and users can successfully create Sub-tasks within the current issue.

 

Is this a known issue? is there any ETA to fix this problem so we won't need to use the workaround?

 

Thanks! 

1 answer

1 accepted

4 votes
Answer accepted
Olga Videc
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 23, 2021

Hello @Bar Abergel 

I see you have been reading community posts, have you read this part 

By Petter Gonçalves ATLASSIAN TEAM 

"If a project has a default assignee but the default assignee does not have the assignable user permission, users will be prompted with the generic error you are seeing when creating a subtask through the new issue view:

Generic error message in the new view when creating a subtask

That being said, can you check if the default assignee under project settings > Details have the "assignable user permission"?"

Does this user have permission to create tasks?

BR, Olga

Bar Abergel June 23, 2021

Hi

I accidentally missed this part :) 

I've changed the project assignee and its working!!! Thank you!!!!

Bar.

Like Olga Videc likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events