The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Using jira for big projects to monitor EV

Chris Tyler
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 13, 2021

I would like to hear from users on how they have broken down large programmes into smaller jira projects and how you control backlog items across projects.

Any tips on using the standard jira toolset for monitoring EV

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Brant Schroeder
Community Champion
May 19, 2021

@Chris Tyler Welcome to the community.  

I have been using Jira for years and have used it for small and large project, program and portfolio work.  A lot of how you do the management of each and break it down will depend on your methodologies and processes.  Jira can be tailored to support this.  As far as monitoring and measuring EV that will depend again on your methodology and what you have defined as EV.  There are some things that you can track in Jira and others you will struggle to.  What are you hoping to monitor as EV?