The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Timeline view - having multiple projects

Rebecca Guest
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 1, 2024

Hi, I want to use the timeline view on my project as it is really helpful to plan in months. However I can't bring items in from other projects. Is there a way around this as I am duplicating tickets to make them appear.

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Matt Parks
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
May 1, 2024

Do you have access to Plans (Advanced Roadmaps)? If so, you should be able to create a plan that brings in all of the work across all projects. Or you could create a plan for each project and then create a program which brings in all of the plans into a single view.