Time tracking report

Hi

On the time tracking report, there is no option to hide the sub-task details.

We have issues which are broken down into tens of sub-tasks and Project managers are not necessarily interested in time tracking of sub-tasks moreover time tracking report also becomes huge with unwanted information.

So, it is possible any way to hide sub-task information. The parent issue anyway shows the accumulated time remaining and time spent metrices which are of primary importance to PMs.

Rahul

1 answer

1 accepted

1 vote
Accepted answer
Daryl Chuah Atlassian Team Mar 24, 2013

Hi Rahul

You can disable the sub-task first before generating the time tracking report.

Hope it helps

Cheers :)

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,425 views 15 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you