Time Spent not updating correctly

Andrea Parimbelli September 15, 2022

Hi all!

 

I have a problem with the time spent on Jira issues.

I have an app that creates / deletes / updates the various worklogs based on an external database.

In the last release of our app there was a problem that created worklog incorrectly, increasing the timespent of some issues by a lot.

Using the rest API v2 we cleared these worklogs, but the timespent remained unchanged.

We tried to modify it via API, but it doesn't seem possible (using API update issue).
We also tried to update the last worklog without data changes with the "adjustEstimate" flag but that doesn't work either.

For example, I have an issue with 3 worklogs of 2h each, but the time spent of the issue is 1w.

how can i change this data?

1 answer

1 accepted

0 votes
Answer accepted
Andrea Parimbelli September 27, 2022

I opened a ticket and seems like a bug at the moment. Escalated to T2 with dev team as support.