Tempo Timesheets update Time Remaining wrongly

Pavel Kovařík July 19, 2023

Hello, 

does anyone have a problem with Tempo Timesheets overwriting the Remaining estimate wrongly?

 

For example: 

how tempo changed.png

Where Original Estimate was 4h, but after logging 1h 30m of work, Tempo changed remaining estimate to 6h 30m. 

Spent .png

2 answers

0 votes
Marta Perez February 6, 2025

Hello @Pavel Kovařík , 

Were you able to get help from Tempo by creating an issue in their portal?

@Morgan DUBUISSON I had the same issue and I fixed it by adding the Log work field in the edit screen. 

It should work correctly when you have both time tracking and log work added in the screens: 

Captura de pantalla 2025-02-06 180500.png

Regards

0 votes
Susanne Götz _Tempo_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 19, 2023

Hi @Pavel Kovařík

Tempo retrives the data for the original and remaining estimates (Estimate and Remaining) from JIRA, as these are native JIRA fields and all calculation is done by JIRA.

When a worklog is created, Tempo updates the Logged information and sends information about the worklog to JIRA. The calculation for the remaining estimate is then done in JIRA, and Tempo retrieves this information from there. 
You might need to refresh the page to show the updated information. 

Best regards,
Susanne Götz
Tempo team 

Pavel Kovařík July 19, 2023

Hi @Susanne Götz _Tempo_ , 

thanks, but unfortunately the refresh didn't help either. I don't want to manually change the remaining estimate field in Jira to maintain continuity. This problem doesn't happen very often, yet I have already noticed it for several issues (1 out of 60).

So is it possible that somewhere there is a unique synchronization problem where first based on worklog 1.5h is added, Remaining is increased and then written as time spent?

Susanne Götz _Tempo_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 19, 2023

Hi @Pavel Kovařík

Can you please create a ticket for this in our Tempo Support portal, https://tempo-io.atlassian.net/servicedesk/customer/portal/6, so we can better investigate this?

As the remaining estimate calculation is done by JIRA, you might also want to reach out to Atlassian.

Best regards,
Susanne

Like Pavel Kovařík likes this
Pavel Kovařík July 19, 2023

Sure, thanks! 

Morgan DUBUISSON
Contributor
January 31, 2024

Good morning,

We are experiencing the same error, can you share the support response with us?