Structure plugin - Question

First let me explain on left side is folder with tasks, that goes the percentage of completition, and sum of story points.

If i have divided tasks to folders and have percentage, can someone explain to me,
what this image shows?

That tasks in "add new campaign step 1" are finished 82%?

If yes that it basically means that there are 184 from 1022 Story Points left

image2016-5-6 18:18:41.png

BUT

When i exclude tasks that are completed i get that there is 471 Story Points left

image2016-5-6 18:13:51.pngimage2016-5-6 18:18:48.png

2 answers

Hello Davor,

Eugene from ALM Works here. Could you please send the screenshot of the progress column settings to support@almworks.com or open a ticket at jira.almworks.com.

There are a few additional options there that affect how the progress is calculated.

It's hard to say why you have these values without seeing these options.

Thanks,

Eugene

The problem was that i haven't set the weight to story points.

Thanks for confirming!

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published yesterday in Jira Service Desk

Wy are we still using email for Service Desk workflows?

...attest to the experience of an urgent approval that gets lost in the boss’s inbox and requires that special “Please Approve” email or text message. In an age where we have distributed teams...

113 views 0 2
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you