when value changes for completed story points in feature issue type. Rule should sum story points [Story points of stories in Done status] and update "completed story points"the respective PI objective issue type.
Relationship is pi objective- feature - story
TPN-17 PI objective
TPN-13 is feature
TPN 15/TPN16 are story in done status and TPN 14 is in To Do status.
Hi @Neeta Dubey ,
I see a space in front of 'Story Points', this might be the reason why it does not work
Hi Rudy,
thanks for pointing this out. That the only reason. I have to remove that extra space. I'm not sure why it didn't throw any error.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It never throws an error, it just does not give a value for the smart value.
Glad to see that it is working now!